Sun River Bridge Replacement
The presolicitation and preliminary letter/plans for MT FLAP BOR 2980(1), Sun River Bridge Replacement have been posted to SAM.gov: https://sam.gov/opp/78e0654a841e48d79a389f2e3a950009/view
Background and Project Description
The Sun River Bridge was originally built in 1916 by the U.S. Bureau of Reclamation as part of the Sun River Project. Its primary purpose at the time was to support and convey an 8-foot-diameter wood-stave siphon pipe across the Sun River. The original design intended for lightly loaded vehicles to travel across the upper truss chord of the single-lane structure, primarily to support Greenfields Irrigation District maintenance duties, although it has also been used by the public since it was constructed. In the 1940s, the wood-stave siphon was removed and replaced with a buried, cast-in-place concrete siphon that passes under the Sun River channel and remains in place today.
The Federal Highway Administration (FHWA) and cooperating agencies are proposing to replace the existing bridge with a new bridge meeting current design and safety standards. The existing Sun River Bridge is in poor condition, and its outdated design poses safety hazards and limitations to users. A new bridge is needed to provide a crossing over the Sun River that safely and reliably accommodates all users.
Cooperating Agencies
- U.S. Bureau of Reclamation (USBR)
- U.S. Bureau of Land Management (USBLM)
- U.S. Forest Service (USFS)
- Greenfields Irrigation District (GID)
Anticipated Timeline
-
Scoping: Spring 2023 (Completed)
-
Public Scoping Meeting: May 16, 2023 (Completed)
-
Project Development & Design: Spring 2023 through Summer 2024
-
Environmental Resource Surveys: Summer 2023
-
Environmental Assessment: Fall 2023 to Spring 2024
-
Environmental Assessment Public Comment Period: February 1 to March 8, 2024
-
Environmental Assessment Public Open House: February 28, 2024 from 3:30pm to 5:30pm
-
NEPA Decision Issued: March 2024
-
Environmental Permitting: Spring/Summer 2024
-
-
Right of Way: Summer/Fall 2024
-
Advertise and Award: Spring 2025
-
Construction – Spring 2025 to Fall 2026
Newsletter
Sun River Bridge Project Environmental Assessment
- Appendix A - Alternatives Analysis Memorandum
- Appendix B - Bridge Inspection Report
- Appendix C - Wetland and Stream Report
- Appendix D - Biological Resources Report
- Appendix E - Biological Assessment
- Appendix F - Summary of Agency and Public Scoping Meetings
- Notice of Availability for Environmental Assessment and Public Meetings
- Approved Environmental Assessment for Public Viewing
- Finding of No Significant Impact
Sun River Bridge Project Section 106 SHPO Consultation Letters
- Letter to Montana SHPO (August 3, 2023)
- Montana SHPO Response to FHWA (August 28, 2023)
- Letter to Montana SHPO (September 26, 2023)
- Montana SHPO Response to FHWA (September 28, 2023)