WFLHD Supplements provide additional information to the FLH PDDM detailing standard practices, guidance, and criteria that pertain to the development of projects within WFLHD.
Highlights
- PS&E Package Signoff Process
- Design Book Assembly
- Documenting Design Exceptions
- Standard Format for Plans
Adopted Supplements Summary of Transmittals
See the individual chapters listed on the left menu or the index below for the current supplements.
Transmittal | Supplement | Description | |
---|---|---|---|
Number | Date | ||
W24 | 9/7/2021 | 9.6.10-1 | Amendment Process |
W23 | 6/2/2021 | 9.6.11-1 | Project Development QC/QA in WFLHD |
W22 | 2/25/2021 | 9.6.2-1 | A+B Bidding (Price + Time) |
9.6.3-1 | PS&E Development at Various Stages of Design | ||
W21 | 1/20/2021 | 5.3.1.1-1 | Horizontal Datum |
W20 | 12/10/2020 | 9.6.4.4-1 | Title Sheet Signatures |
9.6.6.6-2 | PE Hold File Checklist | ||
W19 | 11/17/2020 | 1.1.6-1 | Issuing WFLHD Supplements |
W18 | 3/11/2019 | 9.6.4.5-1 | PS&E Package Signoff Process |
W17 | 2/11/2019 | 9.6.4-1 | CFT and Partner Milestone Review Procedures |
W16 | 10/18/2018 | 1.1.6-1* | Issuing WFLHD Supplements |
9.6.1-2 | Sealing and Signing of Documents Prepared by A/E Firms | ||
W15 | 5/16/2018 | 9.6.10-2 | Release of Digital Design Data for 3D Engineered Models |
W14 | 4/15/2015 | 9.5.9-1 | Land Use Determination for Right-of-Way Coordination |
9.6.11-1* | PS&E Quality in Project Development | ||
W13 | 9/30/2010 | 7.1-1 | Hydraulics Standard Operating Procedures |
9.1.3.4-1 | Documenting Design Exceptions with Form WFLHD-3 | ||
9.6.4-1* | WFLHD Design Review Procedures | ||
9.6.8.5-1 | Development of Prices | ||
9.6.8.6-1 | Assessment of Cost Uncertainties and Risks | ||
9.6.10-1* | PS&E Document Handoff Process | ||
W12 | 3/17/2008 | 9.6.1-1* | PS&E Package Signoff Process |
9.6.4.4-1* | Title Sheet Signatures | ||
9.6.6.2-1 | Design Book Assembly | ||
9.6.8.5-1* | Development of Prices | ||
W11 | 12/17/2007 | 9.6.1-1* | PS&E Package Signoff Process |
9.6.4.4-1* | Title Sheet Signatures | ||
W10 | 10/11/2007 | 9.1.3.4-1* | Documenting Design Exceptions with Form WFLHD-3 |
9.6.3-1* | PS&E Development at Various Stages of Design | ||
13.3.2-1 | External Customer Feedback | ||
W9 | 8/15/2007 | 9.6.1-1* | PS&E Package Signoff Process |
W8 | 5/11/2007 | 9.6.4-1* | WFLHD Design Review Procedures |
W7 | 12/15/2006 | 9.6.6.1-1 | Computation of Quantities |
9.6.6.6-1 | Design Narrative | ||
W6 | 11/9/2006 | 1.1.6-1* | Issuing WFLHD Supplements |
9.6.8.5-1* | Development of Prices | ||
W5 | 11/29/2001 | 9.4.I-1 | Plan Sheet Sizes and WFLHD Details |
9.6.A-1 | Standard Format for Plans | ||
W4 | 10/17/2001 | 1.1.C-1* | Instructions for Issuing Division Procedures |
W3 | 12/9/1999 | 3.4-1 | Environmental Analysis and Public Involvement |
W2 | 9/29/1999 | 4.9.2.5-1 | ERFO Project Development |
W1 | 9/9/1999 | 1.1.C-1* | Instructions for Issuing Division Procedures |
* Supplement was superseded.