FHWA Highway Safety Programs

2013-2016 Comparison

Most states prepared their 2013 through 2016 HSIP reports in accordance with the MAP-21 HSIP Reporting Guidance; therefore FHWA can make a direct comparison of information related to the 2013 through 2016 highway safety improvement projects. As can be seen in Table 3 below, the total number of projects and cost of projects did not change much from 2013 to 2014 but between 2015 and 2016, there were roughly 1000 more projects reported. However, the breakdown in project costs for various breakpoints was similar across years.

Table 1. Total number of projects and project cost breakdown, 2013-2016

Year 2013 Percentage 2014 Percentage 2015 Percentage 2016 Percentage
Number of projects 3292   3348   4188   4468  
Num. of projects (with cost info.)* 3171   3272   3830   3726  
Cost of projects** $3.09B   $3.10B   $3.90B   $4.03B  
Average cost per project $981K   $952K   $1.02M   $1.08M  
 
Number of projects <$100K 1154 35% 1011 30% 1374 33% 1106 25%
Number of projects $100K – $499K 985 30% 1054 31% 1131 27% 1246 28%
Number of projects $500K-$1M 401 12% 450 13% 445 11% 478 11%
Number of projects $1M+ 631 19% 757 23% 880 21% 896 20%
Number of projects with deobligated funds 60 2% 28 1% 146 3% 256 6%
Number of projects with $0 or blank 61 2% 48 1% 212 5% 486 11%

*Number of projects with cost info does not include projects with deobligated funds or where the value entered was $0 or null. **Cost of projects is the sum of total cost for each year (including deobligated funds). Table 2 shows the comparison from 2013 through 2016 of the number of projects and average total cost (does not include deobligated funds or where the value entered was $0 or null) of projects for various project types highlighted in this report. For most project types, the number and cost of projects has increased over the four year period.

 

Table 2. Number of projects and average total project cost for various project types, 2013-2016

Project Type Num Projects 2013 Avg Cost  2013 Num Projects 2014 Avg Cost  2014 Num Projects 2015 Avg Cost 2015 Num Projects 2016 Avg Cost 2016
Urban projects 826 $1.4M 954 $1.3M 1236 $1.2M 1277 $1.7M
Rural projects 1244 $930K 1361 $890K 1847 $1.1M 1683 $956K
 
Roadway projects 854 $639K 722 $955K 1195 $671K 1244 $1.1M
Intersection traffic control projects 420 $682K 505 $702K 615 $798K 608 $704K
Intersection geometry projects 376 $1.3M 379 $983K 559 $1.0M 458 $1.1M
Ped/bike projects 103 $534K 118 $507K 122 $965K 180 $866K
Roadside projects 225 $951K 303 $810K 422 $893K 444 $1.2M