FHWA Highway Safety Programs

THE RSA PROCESS

Eight Steps of an RSA

The eight steps of an RSA are shown in Figure 1, and are discussed below with reference to the case studies.

Figure 1. Flowchart. Flowchart of the eight-step RSA process (click image for alternate description).

FIGURE 1 RSA PROCESS

RSA projects and the RSA team (Steps 1 and 2) were pre-selected in this FHWA case studies project. RSA teams were interdisciplinary, including engineering and enforcement staff. A pavement specialist was included in the case of the Standing Rock Sioux RSA.

All meetings and site visits for the RSAs in the case studies project were conducted over three days. The RSAs typically began with a start-up meeting (Step 3) attended by the Project Owner (hereafter referred to as the Owner), the Design Team (Santa Clara Pueblo only), and the RSA team:

  • The Owner described the tribe's and other users' concerns regarding the roads to be audited, why the sites had been chosen for an RSA, and any constraints or limitations. Typically, the reasons for the RSA site selection centered on high-profile crashes or public safety concerns.
  • For the Santa Clara Pueblo RSA, which included a planning-stage RSA, the Design Team representative then described the future road design, including its constraints and challenges.
  • The multidisciplinary RSA team then described the RSA process. This included an overview of the RSA process with examples of safety issues that are typically encountered and mitigation measures to address them.

Photo. RSA start-up meeting. Participants in a start-up meeting sit around a table looking at photos of the project location.
FIGURE 2
START-UP MEETING

Photo. RSA field review. Members of an audit team inspect guardrail at a project locations.
FIGURE 3
FIELD REVIEW

 

Following the start-up meeting and a preliminary review of the design or site documentation provided by the Owner and Design Team, the RSA team conducted a field review (Step 4). The purpose of the field review was to observe the ambient conditions in which the proposed design would operate (for the planning-stage RSA), or to observe geometric and operating conditions (for the RSAs of existing roads). The RSA team observed road user characteristics (such as typical speeds and traffic mix), surrounding land uses (including traffic and pedestrian generators), and link points to the adjacent transportation network. Field reviews were conducted by the RSA team under a variety of environmental conditions (such as daytime and night-time) and operational conditions (such as peak and non-peak times).

The team conducted the RSA analysis (Step 5) in a setting in which all team members reviewed available background information (such as traffic volumes and collision data). The RSA analysis methodology involved a systematic review of features at the RSA sites, including road geometry, sight distances, clear zones, drainage, signing, lighting, and barriers. Human factors issues were also considered by the RSA team, including road and intersection "readability," sign location and sequencing, and older-driver limitations. On the basis of this review, the RSA team identified and prioritized safety issues, features that could contribute to a higher frequency and/or severity of crashes. For each safety issue, the RSA team generated a list of possible ways to mitigate the crash potential.

At the end of the analysis session, the Owner, Design Team (Santa Clara Pueblo only), and RSA team reconvened for a preliminary findings meeting (Step 6). Presenting the preliminary findings verbally in a meeting gave the Owner and Design Team the opportunity to ask questions and seek clarification on the RSA findings, and also provided a useful forum for the Owner and Design Team to suggest additional or alternative mitigation measures in conjunction with the RSA team. The discussion provided practical information that was subsequently used to write the RSA report.


FIGURE 4
RSA ANALYSIS SESSION

Photo. Preliminary findings meeting. Members from a project owner/design team sit in a room listening to a presentation from RSA audit team members.
FIGURE 5
PRELIMINARY FINDINGS MEETING

 

In the weeks following the on-site portion of the RSA, the RSA team wrote and issued the RSA report (also part of Step 6) to the Owner documenting the results of the RSA. The main contents of the RSA report were a prioritized listing and description of the safety issues identified (illustrated using photographs taken during the site visit), with suggestions for improvements.

The Owner and Design Team were encouraged to write a brief response letter (Step 7) containing a point-by-point response to each of the safety issues identified in the RSA report. The response letter identifies the action(s) to be taken, or explains why no action would be taken. The formal response letter is an important "closure" document for the RSA. As a final step, the Owner and Design Team were encouraged to use the RSA findings to identify and implement safety improvements as and when policy, manpower, and funding permit (Step 8).

Prioritization of Issues

Where reliable crash data were not available (or where a design was being audited), a prioritization framework was applied in both the RSA analysis and presentation of findings. The likely frequency and severity of crashes associated with each safety issue were qualitatively estimated, based on team members' experience and expectations. Expected crash frequency (Table 2) was qualitatively estimated on the basis of expected exposure (how many road users would likely be exposed to the identified safety issue?) and probability (how likely was it that a collision would result from the identified issue?).

Expected crash severity (Table 3) was qualitatively estimated on the basis of factors such as anticipated speeds, expected collision types, and the likelihood that vulnerable road users would be exposed. These two risk elements (frequency and severity) were then combined to obtain a qualitative risk assessment on the basis of the matrix shown in Table 4. Consequently, each safety issue was prioritized on the basis of a ranking between A (lowest risk and lowest priority) and F (highest risk and highest priority). It should be stressed that this prioritization method was qualitative, based on the expectations and judgment of the RSA team members, and was employed to help the Owner and Design Team prioritize the multiple issues identified in the RSA.

For each safety issue identified, possible mitigation measures were suggested. The suggestions focused on measures that could be cost-effectively implemented within likely budget limitations.

TABLE 2 FREQUENCY RATING
ESTIMATED EXPECTED CRASH FREQUENCY (per RSA item) FREQUENCY RATING
EXPOSURE PROBABILITY
high high 10 or more crashes per year frequent
medium high
high medium 1 to 9 crashes per year occasional
medium medium
low high
high low less than 1 crash per year, but more than 1 crash every 5 years infrequent
low medium
medium low less than 1 crash every 5 years rare
low low

 

TABLE 3 SEVERITY RATING
TYPICAL CRASHES EXPECTED (per RSA item) EXPECTED CRASH SEVERITY SEVERITY RATING
crashes involving high speeds or heavy vehicles, pedestrians, or bicycles probable fatality or incapacitating injury Extreme
crashes involving medium to high speed; head-on, crossing, or off-road crashes moderate to severe injury High
crashes involving medium to low speeds; left-turn and right-turn crashes minor to moderate injury Moderate
crashes involving low to medium speeds; rear-end or sideswipe crashes property damage only or minor injury Low

 

TABLE 4 CRASH RISK ASSESSMENT
FREQUENCY RATING   SEVERITY RATING  
low Moderate High extreme
frequent C D E F
occasional B C D E
infrequent A B C D
rare A A B C
Crash Risk Ratings: A:lowest risk level C:moderate-low risk level E:high risk level