CFL Plan Set Organization
Plan Packaging
A standardized approach to the organization of a project plan set provides consistency that enables easier and better plan reviews and allows for locating specific drawings quickly. The guidelines for plan packaging should be used whenever possible. Flexibility in the use of these guidelines is allowed for individual and specific project needs.
Plan Organization |
|
A Sheets |
Title Sheet, Typical Sections |
B Sheets |
Summaries and Tabs |
C Sheets |
Mainline Plan and Profile Sheets |
D Sheets |
Minor Road, Parking, Pullout Plan and Profile Sheets |
E Sheets |
Division 150 Layouts, Standards/Details and Specials (1) |
F Sheets |
Division 200 Layouts, Standards/Details and Specials (1) |
G Sheets |
Division 250 Layouts, Standards/Details and Specials(1) |
H Sheets |
Division 300 Layouts, Standards/Details and Specials (1) |
K Sheets |
Division 400 Layouts, Standards/Details and Specials (1) |
R Sheets |
Division 500 Structural Sheets |
S Sheets |
Division 550 - Structural Sheets |
T Sheets |
Division 600 Layouts, Standards/Details and Specials (1) |
X Sheets |
Mainline Cross Sections |
Y Sheets |
Parking Area, Minor Road Cross Sections |
Z Sheets |
Culvert Cross Sections |
Plan Set Organization Notes
(1) For the order of sheets, layout sheets should be placed 1st, standards/details 2nd, and specials last.
(2) Do not use I, J, and O letter designations to avoid confusion between these letters and the numbers 0 and 1.
(3) The letter designations may be adjusted to fit project-specific requirements. For example, a complicated project may have a lot of T sheets, so the designer may break the T sheets into the following:
a. T Sheets Division 600 sheets (through Section 629)
b. U Sheets Utility layouts and related drawings
c. V Sheets Section 633 and 634 layouts, standards, details, and specials
d. W Sheets Section 635 layouts, standards, details, and specials
Example Index to Sheets
INDEX TO SHEETS |
|
SHEET |
DESCRIPTION |
A1 |
Title Sheet |
A2-A3 |
Conventional Plan and Symbols and Abbreviations |
A4 |
Control Point Listings |
A5-A6 |
Typical Sections |
A7 |
Typical Sections Approach Road |
B1-B5 |
Summary of Quantities |
B6 |
Grading Summary and Mass Haul Diagram |
B7 |
Drainage Summary |
B8-B10 |
Miscellaneous Summaries |
C1-C20 |
Mainline Plan and Profile Sheets |
D1 |
Sacramento Lake Parking Area Plan and Profile |
D2 |
Sunspot Road Intersection Plan |
D3-D4 |
Thousand Mile Canyon Parking/Pullout Plan and Profile |
E1-E11 |
Erosion Control Plan Sheets |
E12-E13 |
157-1 Silt Fence |
F1 |
C204-50 Embankment Benching |
F2 |
207-A Subexcavation and Shoulder Stabilization |
G1 |
C251-50 Placed Riprap |
G2-G3 |
251-A Stream Bank Protection |
G4-G9 |
MSE Wall Layout Sheets |
G10 |
255-A MSE Wall Modular Block Face |
G11 |
255-B MSE Wall Welded Wire Face |
K1 |
401-A Asphalt Curb and Paved Ditch |
S1-S9 |
Bridge Plans for Clear Creek |
S10-S15 |
Bridge Plans for Rio De Las Vacas |
T1-T2 |
601-1, 2 Concrete Headwall |
T3-T7 |
602-1, 2, 3, 4, 6 Pipe Culvert |
T8-T10 |
617-10, 17, 23 Guardrail |
T11-T12 |
619-1, 2, 3 Cattle Guard |
T13-T22 |
633 Mainline Signing and Striping layout |
T23 |
633-A Sacramento Lake Parking Striping Plan |
T24 |
633-B Thousand Mile Canyon Parking Striping |
T25 |
635-1, 2, 3, 5, 6, 8, 14 Temporary Traffic Control |
T26-T28 |
635-A Temporary Traffic Control Site Plan |
T29 |
635-B Detour 28+020 to 28+084 |
X1-X60 |
Mainline Cross Sections |
Y1-Y5 |
Sacramento Lake Parking Area Cross Sections |
Y6-Y10 |
Thousand Mile Canyon Parking Cross Sections |
Z1-Z20 |
Culvert Cross Sections |
Revised 10/5/2022