Stevens Canyon, Phase 2

Project Number: WA PRA MORA 13(5)
Project Name: Stevens Canyon Road Phase II
Bid Opening Date: February 24, 2012

Base Price Indexes

Fuel

OPIS Report Location: Seattle, WA

Week / Date Fuel  ($/gallon)
1 / February 2, 2012 3.05
2 / February 9, 2012 3.16
3 / February 16, 2012 3.24
4 / February 23, 2012 3.36
Base Price Index 3.20

Asphalt Cement

Asphalt Weekly Location: Seattle, WA

Week / Date Asphalt  ($/ton)
1 / February 3, 2012 562.50
2 / February 10, 2012 570.00
3 / February 17, 2012 570.00
4 / February 24, 2012 570.00
Base Price Index 568.13

Computation Approaches Used to Determine Base Price Indexes

Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.

Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.