Base Price Indexes
Fuel
28 Day Average | Fuel ($/gallon) |
---|---|
Base Price Index | 2.52 |
Asphalt Cement
4 Week Average | Asphalt ($/US ton) |
---|---|
Base Price Index | 625.00 |
Computation approaches used to determine base price indexes
Monthly Averages for 2009
Month | Fuel | Asphalt |
---|---|---|
November | 2.04 | 432.50 |
October | 2.03 | 404.00 |
September | 2.02 | 339.38 |
August | 1.96 | 455.00 |
July | 1.72 | 453.00 |
June | 1.88 | 441.25 |
May | 1.62 | 420.50 |
April | 1.58 | 441.25 |
March | 1.27 | 462.50 |
February | 1.32 | 462.50 |
January | 1.55 | 484.00 |
Monthly Averages for 2008
Month | Fuel | Asphalt |
---|---|---|
December | 1.35 | 487.50 |
November | 1.91 | 519.38 |
October | 2.45 | 617.50 |
September | 3.07 | 747.50 |
Computation Approaches Used to Determine Base Price Indexes
Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.
Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.