Teton Park & Signal Mtn Marina
Project Number(s): WY PRA GRTE 11(4) and WY PRA GRTE 112(1)
Project Name: Teton Park Road (Spalding Bay to Jackson Lk Jct) and Signal Mtn Marina Road
Base Price Indexes
Fuel
| Week Ending | Fuel ($/gallon) |
|---|---|
| November 13 | 3.24 |
| November 20 | 2.22 |
| November 27 | 2.13 |
| December 4 | 2.10 |
| December 11 | 2.03 |
| Base Price Index | 2.12 |
Asphalt Cement
| Week Ending | Asphalt ($/metric ton) |
|---|---|
| Week 46 | 498.79 |
| Week 47 | 498.79 |
| Week 48 | 498.79 |
| Week 49 | 498.79 |
| Week 50 | 498.79 |
| Base Price Index | 498.79 |
Computation approaches used to determine base price indexes
Monthly Averages for 2010
| Month | Fuel | Asphalt |
|---|---|---|
| December | 2.63 | 487.80 |
| November | 2.67 | 485.56 |
| October | 2.55 | 482.26 |
| September | 2.32 | 483.63 |
| August | 2.27 | 490.52 |
| July | 2.17 | 498.79 |
| June | 2.22 | 521.39 |
| May | 2.33 | 534.62 |
| April | 2.50 | 536.82 |
| March | 2.32 | 537.37 |
| February | 2.13 | 537.37 |
Computation Approaches Used to Determine Base Price Indexes
Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.
Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.