Agness Road, Phase 2
Project Number: OR FS ARRA FDR 33(4)
Project Name: Agness Road Reconstruction Phase 2
Bid Opening Date: July 23, 2010
Base Price Indexes
Asphalt Cement
Asphalt Weekly Location: Portland, Oregon
Week / Date | Asphalt ($/US ton) |
---|---|
1 / June 28 | 467.50 |
2 / July 5 | 467.50 |
3 / July 12 | 467.50 |
4 / July 19 | 467.50 |
Base Price Index | 467.50 |
Computation approach used to determine base price index
Monthly Averages for 2010
Month | Asphalt |
---|---|
December | 432.50 |
November | 427.50 |
October | 430.00 |
September | 433.13 |
August | 458.50 |
July | 467.50 |
Computation Approach Used to Determine Base Price Index
Asphalt Cement Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.