MT 2009 Pavement Preservation
Project Number: MT PFH 2009(2)
Project Name: MT Statewide 2009 Pavement Preservation Projects
Base Price Indexes
Fuel
Week Ending | Fuel ($/gallon) |
---|---|
October 2 | 2.03 |
October 9 | 2.02 |
October 16 | 2.08 |
October 23 | 2.17 |
Base Price Index | 2.08 |
Asphalt Cement
Week Ending | Asphalt ($/US ton) |
---|---|
Week 39 | 482.50 |
Week 40 | 482.50 |
Week 41 | 470.00 |
Week 42 | 470.00 |
Base Price Index | 476.25 |
Computation approaches used to determine base price indexes
Monthly Averages for 2010
Month | Fuel | Asphalt |
---|---|---|
November | 2.69 | 445.00 |
October | 2.60 | 437.50 |
September | 2.36 | 438.75 |
August | 2.30 | 456.50 |
July | 2.22 | 471.25 |
June | 2.26 | 485.00 |
May | 2.40 | 509.38 |
April | 2.52 | 503.75 |
March | 2.11 | 491.00 |
February | 2.11 | 490.00 |
January | 2.15 | 480.50 |
Monthly Averages for 2009
Month | Fuel | Asphalt |
---|---|---|
December | 2.04 | 474.38 |
November | 2.22 | 470.00 |
October | 2.12 | 472.50 |
Computation Approaches Used to Determine Base Price Indexes
Fuel Price Adjustment: The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.