The project involves improvements at four separate sites along Santa Anita Canyon Road. Site 1 improvements consist of rock fall hazard mitigation. Site 2 improvements are for construction of a Debris Basin and drainage improvements. Site 4 improvements are roadway reconstruction and stabilization. Site 5 improvements include roadway rehabilitation. (**Note: There were originally 5 sites under design. Site 3 has been removed from the project).
Anticipated Timeline
Advertise: Spring 2023
Construction: Summer 2023 - Spring 2024