Order
Subject
FHWA Policy on Permissible Project Related Activities During the NEPA Process
Classification Code Date Office of Primary Interest
6640.1A October 1, 2010 HEPE-1

 

Par.

  1. What is the purpose of this Directive?
  2. Is this a new Directive?
  3. What authorities govern this Directive?
  4. What definitions are used in this Directive?
  5. What is FHWA's policy regarding which project activities may be advanced prior to a National Environmental Policy Act decision?
  6. What activities may be considered preliminary design for purposes of this Directive?
  7. What activities may be considered final design for purposes of this Directive?
  8. What safeguards should be taken to ensure the FHWA does not authorize final design activities?
  9. Should the division administrators report any information to Washington Headquarters?
  10. Will guidance regarding the implementation of this Directive be issued?
  11. Who should I contact for additional information?

  1. What is the purpose of this Directive? This Directive clarifies the Federal Highway Administration's (FHWA) policy regarding the permissible project-related activities that may be advanced prior to the conclusion of the National Environmental Policy Act (NEPA) process.

  2. Is this a new Directive? Yes. This is a new Directive.

  3. What authorities govern this Directive?

    1. Title 23, Code of Federal Regulations (CFR), Section 771.113(a) (23 CFR §771.113(a)) provides the following: "The lead agencies in cooperation with the applicant (if not the lead agency), will perform the work necessary to complete a finding of no significant impact (FONSI) or a record of decision (ROD) and comply with other related environmental laws and regulations to the maximum extent possible during the NEPA process. This work includes environmental studies, related engineering studies, agency coordination, and public involvement. However, final design activities, property acquisition, purchase of construction materials or rolling stock, or project construction shall not proceed until the following have been completed, except as otherwise provided in law or in paragraph (d) of this section:

      1. (1) The action has been classified as a categorical exclusion, or a FONSI has been approved, or a final environmental impact statement has been approved and available for the prescribed period of time and a ROD has been signed;

      2. (2) For actions proposed for FHWA funding, the Administration has received and accepted the certifications and any required public hearing transcripts required by Title 23, United States Code (U.S.C.), Section 128;

      3. (3) For activities proposed for FHWA funding, the programming requirements of 23 CFR, part 450, subpart B, and 23 CFR, part 630, subpart A, have been met.

    2. Title 23, CFR, Section 636.103 (23 CFR §636.103), defines the terms "Preliminary Design" and "Final Design" as follows:

      1. (1) "Final design means any design activities following preliminary design and expressly includes the preparation of final construction plans and detailed specifications for the performance of construction work."

      2. (2) "Preliminary design defines the general project location and design concepts. It includes, but is not limited to, preliminary engineering and other activities and analyses, such as environmental assessments, topographic surveys, metes and bounds surveys, geotechnical investigations, hydrologic analysis, hydraulic analysis, utility engineering, traffic studies, financial plans, revenue estimates, hazardous materials assessments, general estimates of the types and quantities of materials, and other work needed to establish parameters for the final design. Prior to completion of the NEPA review process, any such preliminary engineering and other activities and analyses must not materially affect the objective consideration of alternatives in the NEPA review process."

    3. Title 40, CFR, Section 1502.2(f) (40 CFR §1502.2(f)) provides the following: "Agencies shall not commit resources prejudicing selection of alternatives before making a final decision (Sec. 1506.1)."

    4. Title 40, CFR, Section 1506.1(a) (40 CFR §1506.1(a)) provides the following: "Until an agency issues a record of decision, as provided in §1505.2 (except as provided in paragraph (c) of this section), no action concerning the proposal shall be taken which would:

      1. (1) Have an adverse environmental impact; or

      2. (2) Limit the choice of reasonable alternatives."

  4. What definitions are used in this Directive?

    1. Design-bid-build. The traditional project delivery method where design and construction are sequential steps in the project development process. With the design-bid-build method, a contracting agency may award a design contract to an engineering firm using a qualifications-based procurement process and then, when the design phase is complete, a construction contract will be awarded to a contractor with the lowest responsive bid through a competitive process.

    2. Design-build. A project delivery method where both the design and construction phases of the project are combined into one contract and awarded to a single entity. With the design-build method, the contracting agency may award the contract on a low-bid basis or best value basis through the evaluation of certain factors that are identified in a request for proposals.

    3. Final design. For purposes of this Directive, the term "final design" shall have the same meaning as defined at 23 CFR §636.103, which is stated in Paragraph 3b(1) above, and clarified in this Directive.

    4. NEPA decision. The point in the NEPA evaluation process at which the Federal lead agency issues a CE, FONSI, or a ROD.

    5. Preliminary design. For purposes of this Directive, the term "preliminary design" shall have the same meaning as defined at 23 CFR §636.103, which is stated in Paragraph 3b(2) above, and clarified in this Directive.

    6. Project delivery mechanism. The method used by a contracting agency to deliver a project, including the design-bid-build and design-build methods.

  5. What is FHWA's policy regarding which project activities may be advanced prior to a NEPA decision?

    1. State departments of transportation (DOTs) and other contracting agencies may perform preliminary design activities prior to a NEPA decision regardless of the project delivery mechanism that is used. However, final design activities may not be advanced until a NEPA decision has been issued.

    2. The definitions of preliminary design and final design found at 23 CFR §636.103, and clarified in this Directive, shall be relied upon by the FHWA regardless of the project delivery mechanism used.

  6. What activities may be considered preliminary design for purposes of this Directive?

    1. As specified in the definition of preliminary design, preliminary design encompasses general project location and design concepts. The activities that relate to defining general project location and design concepts are those needed to establish the parameters for final design.

    2. The definition of preliminary design includes examples of specific activities that are needed to adequately analyze alternatives and establish the parameters for final design. These activities are considered preliminary design. However, the activities specified in the definition are not the only activities that are considered preliminary design. Appendix A provides examples of other activities considered to be preliminary design.

    3. The activities specified in the definition of preliminary design and Appendix A are deemed to not materially affect the objective consideration of alternatives or have adverse environmental impacts. However, on a case-by-case basis, if the division administrator believes that special factors are present related to the NEPA analysis, division administrators may determine that one or more activities listed in the definition of preliminary design and Appendix A do materially affect the objective consideration of alternatives in the NEPA review process or have adverse environmental impacts. In such cases, the activity shall not be advanced as preliminary design.

    4. The list of activities in the definition of preliminary design and Appendix A is not exclusive. Other activities necessary to the NEPA decision and that establish the parameters for final design may proceed as preliminary design so long as those activities do not materially affect the objective consideration of alternatives in the NEPA process or have an adverse environmental impact. The determination as to whether any activity materially affects the objective consideration of alternatives or has an adverse environmental impact is a discretionary FHWA determination that is to be made by the division administrator. In making this determination, division administrators should consider the factors identified in Paragraph 6e below. Division administrators may make this determination on a programmatic or case-by-case basis. For activities that are not identified in the definition of preliminary design or Appendix A, division administrators must consult with the Office of Project Development and Environmental Review (HEPE-1) in deciding whether to advance the activity as preliminary design in order to ensure nationwide consistency.

    5. In determining whether any activity that is not needed to complete the NEPA process or to obtain other environmental permits or approvals materially affects the objective consideration of alternatives, division administrators must focus on whether the level of activities advanced prior to the NEPA decision goes too far in focusing on a particular alternative. In making this determination, division administrators may consider and balance any relevant factors, including:

      1. (1) The actual bias on the part of the decisionmaker that the proposed preliminary design activity to be advanced will create with respect to any alternative under consideration;

      2. (2) The perception of bias on the part of the community at large with respect to the advancement of the proposed preliminary design activity;

      3. (3) The extent to which the proposed preliminary design activity is specific to only one alternative under consideration;

      4. (4) The degree of preliminary design activities advanced for any given alternative relative to other alternatives under consideration;

      5. (5) The estimated cost of the proposed preliminary design activity standing alone is substantial; and

      6. (6) The degree to which the proposed preliminary design activity relates to any specific point of controversy regarding an alternative under consideration.

    6. In all cases, regardless of what activities are advanced prior to a NEPA decision, division administrators must exercise independent judgment and retain the discretion to approve any reasonable alternative under consideration. Division administrators retain this discretion regardless of the amount of preliminary design activities advanced (in terms of both quantity and cost) for any alternative.

  7. What activities are considered final design for purposes of this Directive?

    1. The activities in the definition of final design are considered to be final design. Other activities constituting final design include final plans, project site plan, final quantities, and final engineer's estimate for construction.

    2. Activities considered to be advanced as preliminary design for a project but rejected as materially affecting the objective consideration of alternatives or having an adverse environmental impact are considered final design.

  8. What safeguards should be taken to ensure the FHWA does not authorize final design activities?

    1. In project agreements in which Federal funds are authorized for preliminary engineering, a notation should be made that Federal funds are authorized only for preliminary design.

    2. The execution or modification of a project agreement to authorize final design for design-bid-build projects shall not occur until after the NEPA decision. Also, as provided at 23 CFR §636.106(a)(7), the execution or modification of the project agreement to authorize final design and physical construction for design-build projects shall not occur until after the NEPA decision. However, preliminary design activities may be authorized for both design-bid-build and design-build projects.

    3. Division administrators shall work with their State DOTs to develop State specific preliminary design policies for:

      1. (1) Direct oversight projects;

      2. (2) State administered projects;

      3. (3) Local public agency projects; and

      4. (4) Design-bid-build, design-build, and other project delivery methods that may be used in that State.

    4. For design-build projects, a contract may be awarded prior to the NEPA decision. In these cases, the contract should be divided into two phases, such as "notice to proceed 1" and "notice to proceed 2." The work in "notice to proceed 1" should be limited to preliminary design, and the work in "notice to proceed 2" should include final design and construction. The contract should clearly state that no commitment is being made to any alternatives under consideration in the NEPA process, that all alternatives will be fairly considered, and that the issuance of "notice to proceed 2" is conditioned upon the selection an alternative in the NEPA decision. You should refer to 23 CFR §636.109 and §636.302 for the express regulatory requirements regarding the release of a request for proposals and award of a design-build contract prior to a NEPA decision.

  9. Should the division administrators report any information to Washington headquarters?

    1. Starting on September 30, 2011, and each year thereafter, division administrators will submit a report to the Office of Project Development and Environmental Review listing whether the Division has executed an agreement with the State DOT to develop State- specific preliminary design policies in accordance with this Directive.

    2. Starting on September 30, 2011, and each year thereafter, division administrators will submit a report to the Office of Project Development and Environmental Review identifying the activities permitted to be advance as preliminary design that are not listed in the definition of preliminary design or Appendix A.

  10. Will guidance regarding the implementation of this Directive be issued? Appendix B to this Directive contains guidance and explanatory notes regarding the issuance and implementation of this Directive. Additional guidance may be issued in the future as needed.

  11. Who should I contact for additional information?

    Project Development Team Leader
    Office of Project Development and Environmental Review (HEPE-10)
    202-366-1598

    Pre-Construction Team Leader
    Office of Program Administration
    202-366-2221

    Senior Attorney Advisor
    Office of Chief Counsel
    202-366-4928

 
Mendez signature

Victor M. Mendez
Administrator

Attachments