Vehicle-to-Infrastructure Communications for Safety Concept of Operations (ConOps) Documentation

Project Information

Project ID: 
FHWA-PROJ-11-0064
Project Status: 
Completed
Start Date: 
Tuesday, September 6, 2011
End Date: 
Thursday, January 31, 2013
FHWA Program: 
Safety
FHWA Subprogram: 
Safety Data and Analysis
FHWA Activity: 
Vehicle to Infrastructure
FHWA Topics: 
Research/Technologies--FHWA Research and Technology
TRT Terms: 
Applications; Intelligent Transportation Systems; Safety; Research; Systems Engineering; Highways; Vehicles
FHWA Discipline: 
Safety
TRB Subject Area: 
Highways, Research

Contact Information

First Name: 
Gregory
Last Name: 
Davis
Telephone: 
(202) 493-3367
Email Address: 
Team: 
Roadway Team
Office:
Office of Safety Research and Development
Office Code: 
HRDS-10

Project Details

Project Description: 

This project will develop a concept-of-operations document for Vehicle-to-Infrastructure (V2I) safety applications. The contractor is tasked with engaging the stakeholder community, conducting workshops, identifying applications and user needs, and developing appropriate documentation that describes the concepts of each application.

Deliverables

Deliverable Name: 
Vehicle-to-Infrastructure (V2I) Safety Applications Concept of Operations
Deliverable Type: 
Other
Deliverable Description: 
This document describes the Concept of Operations (ConOps) for five connected vehicle vehicle-to-infrastructure (V2I) safety applications, and the underlying connected vehicle system, for crash avoidance for the U.S. Department of Transportation (USDOT). The ConOps describes the current state of roadway safety operations across the country regarding intersection safety, rail crossing safety, weather impacts, oversize safety, and work/speed zones; establishes the reasons for change; and describes the selected connected vehicle V2I safety applications in terms of their features and operations by: • Capturing and documenting user needs as they relate to connected vehicle V2I safety applications. • Describing the safety applications and connected vehicle system functions in nontechnical language from the user’s point of view.
Deliverable Name: 
Final concept of operations report
Deliverable Type: 
Research report or guidelines
Deliverable Description: 
The deliverable is a final report of the Safety Concept of Operations effort.