Pavement Preservation Lake Roosevelt

Project Overview

The project will provide micro surfacing pavement preservation treatments on various roads, parking lots, and view points in the Lake Roosevelt National Recreation Area. The pavement preservation treatments will extend the life of the asphalt pavements. The project will include pavement patching, crack sealing, micro surfacing, and pavement markings and signs.

The project is consists of 3,650 square yards of patching, 18 miles of crack sealing, 375,000 square yards micro surfacing, and pavement marking on 16 miles of roads, parking areas and viewpoints from China Bend to Grand Coulee Dam.

Newsletters

Anticipated Timeline

Construction: Summer 2019 - Spring 2020

Project Completion: Summer 2020