You are here

Okanogan-Wenatchee 2017 Repairs, Phase IV

Project Description

Volstead Road is located in the Okanogan-Wenatchee National Forest, southeast of Winthrop, WA.  A 1.6 mile section of the roadway was severely damaged during a 2017 flooding event.  The decision was made to decommission this section of the road rather than repair it. The decommissioning includes scarifying of the roadway, grading to restore original ground contours if possible,  the removal and disposal of 10 - 48 inch diameter culverts and seeding after decommissioning. 

Project Area

Anticipated Timeline

  • Advertise:  Spring 2020
  • Construction: Fall 2020
  • Project Completed: Fall 2020