Okanogan-Wenatchee 2017 Repairs, Phase III

Project Description

In January and February of 2017, a major storm caused damage to roads within the Okanogan-Wenatchee National Forest. These roads provide recreational and administrative access to the National Forest. The Emergency Relief of Federally Owned Roads (ERFO) program will be used to restore these damaged roads to their original condition.

Scope of Work

Phase III contains eleven sites with individual scopes of work ranging from slope repair to replacing culverts and installing aquatic organism pipes, rebuilding road structure and replacing eroded road surface materials.

Newsletters

Anticipated Timeline

  • Project Kick Off: Summer 2018
  • 95% Plans, Specifications, & Estimates (PS&E): Spring 2019
  • 100% PS&E Delivery: Summer 2019
  • Contract Advertisement: Summer 2019
  • Construction: Fall 2019 - Fall 2020