Gifford Pinchot Repairs 2017

Project Description

During the winter of 2017, a major storm caused damage to several roads within the Gifford-Pinchot National Forest (GPNF). These roads provide access to recreation sites and administrative access to forest service personnel. The Emergency Relief for Federally Owned Roads (ERFO) program will be used to restore the damaged roads to their original condition. GPNF has made minor repairs to some of the roads where possible to prevent further damage or worsening their current condition.

Project Partners

  • United State Forest Service – Gifford-Pinchot National Forest (GPNF)
  • Federal Highway Administration – Western Federal Lands Highway Division (FHWA-WFLHD)

Scope of Work

There are thirteen sites that require repairs to return the roads to their original condition. They are summarized below. (The abbreviation MP stands for milepost.)

Road # and MPDescription of work

54-26.9

Removed and replace failed culvert, embankment, aggregate base and asphalt surface

63-12.0

Debris removal, reconstruct road embankment, clean up cut slope and provide for 10’ wide rock catchment ditch

88-19.7

Replace damaged culvert with Aquatic Organism Passage (AOP) culvert

88-19.8

Replace damaged culvert with AOP culvert

90-11.5

Repair slope failure/slide, stabilize and revegetate slope, obtain temporary right of way (R/W)

90-28.0

Survey road and design and AASHTO vertical alignment that will pass vehicles with trailers and RVs

90-44.8

Removed and repair pipe culvert with a 100 year storm pipe and reconstruct the embankment

99-4.9

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-5.1

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-5.3

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-5.4

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-7.5

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-8.4

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-8.69

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-10.5

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

99-11.0

Emergency repair completed, permanent repair to include asphalt paving and hauling of failed asphalt

Anticipated Timeline

  • November 2018 - Project Kick-off
  • July 2019 - 70% Plans, Specifications and Estimate (PS&E)
  • August 2019 - 95% PS&E
  • October 2019 - 100% PS&E
  • Winter 2020 - Contract Advertisement
  • Summer 2020/2021 - Construction