Project Description
| Project Number | Description | Status |
|---|---|---|
| VI ST ER STX (001) | Repair damaged Traffic Signal Systems and Roads at several locations on St. Croix | Construction is estimated to be completed in the Spring of 2019. |
| VI ST ER STT (001) | Repair damaged Traffic Signal Systems and Roads at several locations on St. Thomas | Construction is estimated to be completed in the Summer of 2019. |
| VI ST ER STX (002) | Repair damaged Traffic Signal Systems and minor Road repairs on St. Croix | Construction is estimated to be completed in the Spring of 2019. |
| VI ST ER STT (002) LC | Repair Additional Damaged Traffic Signal Systems at 13 intersections and repair Roads on St. Thomas | Construction is estimated to be completed in the Summer of 2019. |
Anticipated Timeline
Award: Fall 2017 - Spring 2018
Construction: Fall 2017 – Winter 2019/2020