Project Number, Description, and Status
Project NumberDescriptionStatus
VI ST ER STX (001)Repair damaged Traffic Signal Systems and Roads at several locations on St. CroixConstruction is estimated to be completed in the Spring of 2019.
VI ST ER STT (001)Repair damaged Traffic Signal Systems and Roads at several locations on St. ThomasConstruction is estimated to be completed in the Summer of 2019.
VI ST ER STX (002)Repair damaged Traffic Signal Systems and minor Road repairs on St. CroixConstruction is estimated to be completed in the Spring of 2019.
VI ST ER STT (002) LCRepair Additional Damaged Traffic Signal Systems at 13 intersections and repair Roads on St. ThomasConstruction is estimated to be completed in the Summer of 2019.

Anticipated Timeline

Award:  Fall 2017 - Spring 2018
Construction:  Fall 2017 – Winter 2019/2020