You are here

Warren Wagon Road, MP 7.9 to 9.7

Project Description

The work on Warren Wagon Road west of Payette Lake is largely complete. A new project, scheduled to start construction in late spring 2020, will start north of East Side Road and end just south of Fischer Creek Bridge. Key Project Elements include:

  • Construct Frost-resistant pavement
  • Stabilize areas of shallow roadway slides
  • Reconstruct sharp curve with standard roadway crown and signs
  • Replace old guardrail
  • Install culverts to improve drainage

Contractor’s Public Information Office

Crea Construction, Inc.
1508 Tammany Creek, Rd.
Lewiston, ID 83501
Phone: (208) 746-3072

Contractor's Public Information Contact

Bryan Peters, Public Information Officer
(208) 503-2032

Anticipated Road Closures

The road is open to public traffic, no further delays are anticipated.

Project Partners

  • Valley County
  • Federal Highway Administration – Western Federal Lands Highway Division

Newsletters

Anticipated Timeline

  • Contract Advertisement & Award – Winter 2019/2020
  • Construction – Late Spring/Summer 2020
  • Anticipated Completion – Fall 2020
  • Project Completed - Fall 2020

Project Photos