Project Description

The proposed project includes rehabilitation, resurfacing, and restoration of approximately 10.6 miles of Glacier Point Road from Badger Pass to the Glacier Point Parking Area and pavement preservation of approximately 5.1 miles of Glacier Point Road from Chinquapin to Badger Pass. Work also includes construction of 2 retaining walls, subgrade stabilization, drainage improvements, including culvert cleaning and replacement, and rehabilitation/reconstruction of multiple parking areas including Sentinel Dome Trailhead, Washburn Point and Glacier Point. The existing roadway consists of aging and deteriorated pavement, failed drainage structures, and informal pullouts and roadside parking. Roadside pullouts will also be formalized or removed to improve safety.

Anticipated Timeline

Advertise Date: December 2019
Construction Date: Spring 2021 – Fall 2022